Installation and Construction Requirements for Outdoor Display
Beloong Group, as the leading manufacturer, wholesaler, engineering project contractor, and constructor of Commercial Display Equipment in China, has undertaken many large-scale key engineering projects at home and abroad, and has cooperated with the government on numerous projects. Experience professional and thoughtful service.
Such as DOOH, there are a lot of original instructions.
Concrete Base :
(1) Dig a 600MM deep pit on the ground.
(2) Put the pre-welded rebar into the reclamation as required (rebar in accordance with GB1499.2-2007 standard.
(3) Buried cables (requires 2M exposed to the ground, and cables are required to carry 3000W of power consumption.
(4) Pour in concrete (concrete is in accordance with GBT-50107-2010 standard).
(5) Let it dry for 24 hours (when it is dry, it is required to cover the ground concrete base with a plastic sheet).
Outdoor Digital Signage installation
(1) Disassemble the outer packaging of the Digital Equipment first;
(2) Put the steel rope of the crane into the ring hole on the Digital Equipment;
(3) When the Digital Equipment is lowered, it is required to align the threads of the pre-buried concrete base (note that the power cord needs to be inserted into the cabinet);
(4) After inserting, set the nut, adjust the level, and tighten the nut;
(5) After connecting the power supply, the installation is completed.